Modernization of energy infrastructure facilities

Comprehensive modernization of generation and grid assets: replacement of a 6 MW turbine at an operating thermal power plant and construction of a 110/10 kV substation with modern automation and relay protection systems

Energy infrastructure
Completed
Turkmenistan, Turkmenabad
State energy company / operator of a thermal power plant (within the framework of the TPP modernization project) and a state customer of an infrastructure facility (within the construction of a 110/10 kV substation for Turkmenabad airport).

FOR WHOM

The operation of worn-out generating equipment and the need to improve the reliability of power supply required the technical modernization of energy facilities, within which projects were implemented to replace a turbogenerator at an operating thermal power plant and to construct a primary 110/10 kV substation for a new infrastructure facility, while all work was carried out without interrupting critically important power supply.

CONTEXT

To ensure increased reliability and service life of generating equipment, compliance with modern automation and safety requirements, as well as the development of a sustainable energy infrastructure for new facilities.

GOAL

SOLUTION

Construction of a primary 110/10 kV substation
installation of power transformers
integration of the facility into the existing power system
implementation of relay protection and automation systems
design and construction of switchgear
Replacement of a 6 MW turbine at a thermal power plant
installation of a new turbogenerator of equivalent capacity
installation of new automation and engineering support systems
reconstruction of the reinforced concrete foundation
dismantling of the worn-out unit

RESULT

Generating equipment upgraded without reducing installed capacity

A new substation infrastructure has been created to supply power to a large infrastructure facility
Compliance with modern industrial and electrical safety requirements has been ensured
Operational reliability of equipment has been increased
Reduction of accident rates and operational risks, extension of the lifecycle of energy assets, increased resilience of the power system to peak loads, and creation of a reserve for further industrial and infrastructure development of the region.